Pre-start defects on mine sites: who owns the follow-through
The mining rules are clear at both ends: every defect is reported, and the dangerous ones are fixed before the machine is used. The decisions in between, who assesses the defect, what happens to the machine meanwhile, and how long a repair can wait, are the ones sites most often leave to habit.
Published 5 min read9 sources
Written for site and project supervisors · fleet maintenance managers · mining and construction safety managers
What the rules require
Queensland's coal mining regulation sets out the shape of the duty in two lines. A mine's safety and health management system must provide for 'reporting all defects in the mine's plant, structures and procedures' and 'rectifying defects that create an unacceptable level of risk'.[1] Every defect is reported; not every defect has to be fixed at once. The same regulation requires the operator, 'as soon as practicable after taking control of the plant, to check that the plant's brakes, steering, lights and any other safety features are functioning properly'.[1]
The NSW Resources Regulator's code of practice for mechanical engineering control plans describes the system that should sit behind that, including 'a means to prevent the use of mechanical plant or structures until a defect has been assessed by a person with appropriate mechanical competence e.g. the use of ‘danger’ or ‘out of service’ tags', 'recording action taken to remedy or control the defect', and 'a competent person reviewing the plant or structure and verifying it is safe to use'.[2] On construction sites, SafeWork NSW's code for moving plant is blunter: 'All safety-related faults must be reported and corrected before the plant is used.'[3]
This article follows the mining rules. For construction sites under the general WHS law, and what inspectors found there in 2025 and 2026, see What Queensland and NSW regulators expect after a failed pre-start.
Who does what
Read together, the instruments assign each step to a different person, and most follow-through failures happen where one hands over to the next.
- The operator checks, reports what they find, and does not use the plant if a safety feature is not working. They also need to know which items stop the machine. A 2024 NSW campaign at small mines found many workers 'did not know what action to be taken if a safety critical item was not operational', and asked sites to make clear 'which safety critical items mean that the plant cannot be operated till the issue is rectified'.[4]
- The supervisor decides what happens to the machine now: tagged out, restricted, or allowed to continue, and makes sure the defect reaches whoever maintains it.
- The maintainer assesses the defect mechanically, repairs it, and records what was done.
- A competent person, often an engineer, decides whether a defect can be lived with for a time and on what conditions, and verifies the plant is safe before it is used again.
- The owner, where the plant is hired or contracted. In a NSW case, a hired dump truck's pre-start found a faulty fuel gauge that was reported to the mine, 'however there was no record of it being passed onto the equipment owner (contractor) for repair and it was not repaired'. The truck later ran out of fuel on a ramp and rolled back 48.8 metres when its service brakes failed to apply.[5]
Deferral is a decision, and needs an end
None of the instruments above sets a maximum time a defect can be deferred. They leave it to the site's risk-assessed system and a competent person, which is reasonable, because the right answer for a cracked step and a weeping brake line are not the same. Queensland's mineral mining regulation frames the question well: monitoring of plant must 'decide if the plant is likely to operate without causing an unacceptable level of risk until the plant is next monitored'.[6]
The NSW fluid power guide offers a useful model for hoses that generalises: a competent person decides whether an item 'is fit for continued service', 'is fit for limited service', or 'should be replaced immediately'.[7] 'Limited service' is a deferral with its terms stated. A deferral written down that way has four parts:
- who decided, and on what assessment;
- the interim controls: a restriction on use, more frequent checks, or a condition that ends the deferral early;
- an expiry: a date, a number of hours, or the next scheduled service;
- the work that will close it, raised and visible, so the deferral does not simply become the new normal.
Where follow-through fails
The regulator's own inspections suggest the process often lives in people rather than in procedure. Its 2018 review of fires on mobile plant at 25 open-cut coal mines found workers had a good understanding of 'the process for reporting, temporary repair or stand down and replacement of hoses despite only two mines having a formal procedure or a trigger action response plan (TARP)'.[8] That works until the experienced people are not on shift.
The pre-start record itself can also drift from reality. A 2025 NSW bulletin on mobile crushing and screening plant found a worker had knowingly started a machine in travel mode to get round a faulty lanyard, while 'pre-start records indicated lanyards were operational'.[9] A pre-start that is always clean on a machine with known faults is itself a signal worth looking at. What six incident reports say about defects that were already known has more cases where the defect was on record before the incident.
What to write down before the next defect
- Which pre-start items stop the machine, by machine class, and what the operator does when one fails.
- Who is told, how, and within what time, including the owner or hire company where the plant is not yours.
- Who may defer a repair, on what assessment, with what interim controls, and until when.
- How a repair is verified and who may return the machine to use. Three decisions before a machine goes back to work covers that step.
Mainte's handling of the same sequence, from a failed pre-start item to an authorised return to service, is described in From a failed check to a safe return to service.
Sources
- [1]Coal Mining Safety and Health Regulation 2017 (Qld), sections 71, 73 and 98 · Queensland Government (Queensland Legislation) · Current in-force version · Regulation
- [2]Code of practice: Mechanical engineering control plan (version 4.0) · Resources Regulator, NSW · May 2025 · Approved code of practiceQuoted from section 4.5.6.
- [3]Code of practice: Moving plant on construction sites · SafeWork NSW · December 2025 · Approved code of practice (NSW)Quoted from Appendix B.
- [4]Small mines high visibility campaign: results · Resources Regulator, NSW · 2025 · Regulator campaign report
- [5]Safety Alert SA22-05: Service brakes fail on moving articulated dump truck · Resources Regulator, NSW · October 2022 · Regulator safety alert
- [6]Mining and Quarrying Safety and Health Regulation 2017 (Qld), section 108 · Queensland Government (Queensland Legislation) · Current in-force version · Regulation
- [7]Technical reference guide TRG 41: Fluid power safety systems at mines (version 2.0) · Resources Regulator, NSW · March 2025 · Regulator technical guidanceSection 7.6.2.1.
- [8]Consolidated report: assessment program, fires on mobile plant in open cut coal mines · Resources Regulator, NSW · November 2018 · Regulator planned inspection report (25 mines)
- [9]Safety Bulletin SB25-07: Bypassing lanyard safety systems on mobile crushing and screening equipment · Resources Regulator, NSW · December 2025 · Regulator safety bulletin